Step by Step Installation

 

 

Step 1

 

The Empty Furnace.

Step 2

 

Position the mica slip-plane.

Step 3

 

Tape the mica into position.

Step 4

Pour in the lining for the base and vibrate.

Step 5

 

Measure Depth.

Step 6

 

Trim the spider wire.

Step 7

 

Ensure the former is clean.

Step 8

 

Position the former level and secure.

Step 9

 

Pour in the lining to just above the chamfer.

Step 10

 

Spike the lining.

Step 11

 

Top up the lining material around the chamfer.

Step 12

 

Vibrate the lining around the chamfer.

Step 13

 

Top up the Lining.

Step 14

 

Vibrate the lining using the <br>internal vibrator and top up.

Step 15

 

Vibrate.

Step 16

 

Complete the vibration, reducing power at the top.

Step 17

 

Spike the lining top.

Step 18

 

Add the topping and spike into the lining.

Step 19

 

Ram the lining in.

Step 20

 

Put holes in the topping to release steam during sintering.

Step 21

 